Done?!
We completed all tasks... I always worry (superstition?) when I say this, but: We're done. I am grateful for the superb team who built and executed the plan: They ROCK!
Upgrade information published in a fun yet meaningful way.
We completed all tasks... I always worry (superstition?) when I say this, but: We're done. I am grateful for the superb team who built and executed the plan: They ROCK!
Backups are complete. We are rebooting servers, restoring "public" user interfaces, and performing final verifications... almost there.
The db server OS work and database work are done. The application group is near completion. The night worker were succeessful and fast. We are nearly 2 hours ahead of schedule.
Vinny is nearing the end of OS modifications to db server. He is about 30 minutes from handing off to Lennie. We're estimating we are 30+ minutes ahead of schedule and are likely to pick up more time in the next set of DBA changes.
The Banner midtier servers are small; their backups ran quickly. After Vinny completed the backups, Lennie applied Oracle security patches. Vinny is rebooting the midtiers to assure all is well.
Before we make changes we make certain we have a safe copy of the working (pre-upgrade) system and data. While this happens, we wait. Backups should finish around 7:30. Expect more news shortly after that.